585, Construct detached garage, gra, Studies & ReportsRESIDENTIAL DRAFTING SERVICE INC.
3706 Woodruff Ave. Long Beach, California, 90808 - 2123.c HILLS
Ph. (562) 421 - 0919 Fax. (562) 420 - o�
pppsoved
PLANNING DEPARTMENT
March 4, 1999
Mrs. Lola M. Unbar
Planning Dept. City of Rolling Hills
# 2.Portuguese Bend Road
Rolling Hills, Calif. 90274
Date �ct:YZ '77b
:.�l11 pvp�T
Ph. (310) 377 - 1521 401
Fax. (310) 377 - 7288
Subject: Bob Barth New Garage, Zone Case 585, 29 Portuguese Bend Road
Additional Grading Required per Soils Engineers Report.
Dear Lola;
Original design and Site Plan indicated a Two to Three Foot Stem Foundation wall on rear and Right
Elevation. In discussions with the Rolling Hills Community Association, they indicated the Foundation
Stem wall was not desirable. The requested a Three Foot flat area around Garage, on Rear and Right
Elevations and raise grade elevation to within 6" of top of Foundation Curb.
The existing grade slope is approximately 4 to 1. With raising the grade around the Garage, this in turn
extended the 2 to 1 slope, and increased the bottom of slope out from Garage from approximately Ten
Feet to approximately Twenty Five feet.
My original Foundation Design was to use continuous Footing, depth into grade as required or into
Bedrock. When the Soils Report was requested, it indicated that the ground would not support the
Garage Floor or Footings.
The Soils Report requested a 27 inch deep footing into recompacted, engineered fill, minimum Three
Feet below bottom of Footing, with Keyway at bottom of Slope. This increase the cut - fill from the
original expected 15 Cubic Yards to the engineered cut and fill of approximately 202 cubic yards and
imported or soil gathered from Site to approximately 320 Cubic Yards.
Mr. Barth applied for a Building Permit on October 7, 1997, and was due to expire on October 7,1998.
The Soils report took Three Months to obtain and then had to revise structural engineering. We applied
and received a Six month extension for permit, extended to March 7, 1999. Plans now are in L.A. Co.
Building Dept, Lomita Office for recheck. Now need to apply for Geology and Grading Permits before
Building Department will issue Building permit. Will have Rolling Hills approved Final plans, before
permits issued.
Sincerely Yours,
,1a6errt Cf. V e W(o
Draftsman, President
_Western Laboratories
1 .
Geotechnical Engineering
March 1, 1999 Work Order 98-2556
MR ROBERT BARTH
#29 Portuguese Bend Road
Rolling Hills, California 90274
Subject: Addendum No. 2
Geotechnical Engineering &
Engineering Geologic Investigation
Proposed Garage
#29 Portuguese Bend Road
Rolling Hills, California
Dear Sir:
CITY OF ROLLING HILLS
Approved T,G aff,
PLANNING DEPARTMENT
Date
At the request of Mr. Bob Demoss, this addendum to our Geotechnical Engineering and
Engineering Geologic Investigation, dated July 15, 1998, Work Order 98-2556, is submitted.
We have been asked to address three statements presented by the City of Rolling Hills with
regard to the proposed grading operation to be performed at the subject property. The
statements are repeated herein and a copy of the statements are attached.
3. (a) construction of a structure on the lot or parcel has commenced,
It is the understanding of this firm that the permit application is approaching it's expiration
date. Construction of the garage on the lot has not commenced.
3. (b) that the need to import or export the soil could not have been foreseen prior
to commencement of construction, and
The engineering reports require that the existing fill and colluvium be removed and
recompacted. A keyway should be excavated at the toe of the fill slope and the bedrock
should be benched as the grading operation progresses.
3. (c) that either the structure cannot be completed without the requested import or
export of soil or that an emergency condition exists due to the threat of land
subsidence or other imminent danger.
Grading operations will be required to provide foundation and slab support.
3665 West 240th Street, Torrance, CA 90505 (310) 791-9001 — FAX (310) 791-0248
March 1, 1999 Work Order 98-2556
We appreciate this opportunity to be of service to you.
• Very truly yours,
WESTERN LABO ' • e_
��FES
Kirk S eller
Senior Engineer
R.C.E. 4
2
Western Laboratories
v Geotechnical Engineering
15.04.170
2. No grading plan for which a permit is required
shall be approved unless the amount of soil to be cut
from the site equals the amount of soil to be filled
on the site.
3. The City Manager may grant an exception to the
requirements of parts 1 and 2 of this paragraph to
allow for the import or export of soil not to exceed
500 cubic yards if he or she finds, based upon written
reports and other information submitted, that all of
the following conditions are present:
construction of a structure on the lot or par-
cel has commenced,
(b) that the need to import or export the soil
could not have been foreseen prior to commencement of
construction,.. and
(c) that either the structure cannot be completed
without the requested import or export of soil or that
an emergency condition exists due to the threat of
land subsidence or other imminent danger.
4. The City Manager may grant an exception to the
requirements of parts 1 and 2 of this paragraph to
allow for the import or export of soil not to exceed
500 cubic yards for remedial repair of a hillside or
trail if he or she finds, based upon written reports
and other information submitted, that all of the fol-
lowing conditions are present:
(a) the project does not require a grading permit
(a cut that is less than three feet or a fill that is
less than three feet or covers less than 2,000 square
feet), and
(b) the import or export of soil is no greater
than necessary to avoid a threat of land subsidence or
other imminent danger.
(Ord. 273 §5, 1998: Ord. 257-U §1(part), 1995).
174-1 (Rolling Hills 4/98)
FAX COVER SHEET
Wednesday, March 03, 1999 11:14:18 AM
To: Lola Unbar
At: Rolling Hills Planning
Fax #: 13103777288
From: ROBERT DeMOSS
Company: RESIDENTIAL DRAFTING SERVICE INC.
Fax #: 562-420-3359
Voice: 562-421-0919
Fax: 2 pages and a cover page.
Wednesday, March 03, 1999 11:14:18 ,RESIDENTIAL DRAFTING SERVICE INC. Page 1 of 2
March 2, 1999
Mrs. Lola M. Unbar
Planning Dept. City of Rolling Hills
# 2 Portuguese Bend Road
Rolling Hills, Calif. 90274
:13 EgEHET))1
MAR 0 31999
CITY OF ROLLING HILLS
!�V
Ph. (310) 377 - 1521
Fax. (310) 377 - 7288
Subject: Bob Barth New Garage, Zone Case 585
Additional Grading Required per Soils Engineers Report.
Dear Lola;
At time of obtaining City of Rolling Hills approval for Garage, the existing Soil conditions where
unknown. Construction has not started, but we are in the process of obtaining required permits. Mr. Barth
obtained a Building Plan Check Extension, on September 16 th. to extend time to obtain permit until March
7 th. 1999. Due to Work overload, Residential Drafting Service Inc. has been behind in getting
Engineering and Plans revised for submittal. The Building plans have now been revised, regarding
Structural Engineering, and are in for Structural recheck at this time at the Lomita Office, Los Angeles
County Building Department.
The Soils Engineer, Western Laboratories of Torrance, California is requiring excavation of area at
proposed Four Car Garage from Four feet up to Eight Feet deep, than reuse soil and recompact for
Garage. To bring exterior grade up to within Six Inches of top of Foundation, and raise grade to provide a
level pad for Garage is going to require obtaining additional soil from site or possibly importing soil.
The Soils Report is requiring a minimum of Three Feet of Engineered, Compacted Soil under the required
Twenty Seven inch deep footing along with a earth key way at bottom of slope.
This is requiring us to submit Grading Plans plans to Los Angeles County Grading, Geology Division
for Grading Plan Check which we need to do this week. Our Los Angeles County Plan check expires March
7 th. but if the Grading Plans are in Plan check we have a Thirty Day Extension to April 6 th. to obtain
permits.
Seaboard Engineering is now preparing this Grading Plan, and will have complete this afternoon, and
I will deliver to you this afternoon. As the Grading Office is closed on Friday, I need to submit these grading
plans no latter than Thursday, March 4 at the Alhambra Office, County Building Dept. Grading Division.
According to the revised Grading Plan, this amounts to removing and recompacting approximately
202 Cubic Yards and obtaining from site or importing approximately 320 Cubic Yards of Soil, all to be
compacted per Soils Report for 2 : 1 Slope. Exposed slopes and area outside of Garage to be landscape to
control erosion. The original estimation of 15 Cubic Yards of removed and recompacted soil did not take in
account of Soils report, which we did not have that time.
Would appreciate your approval of extra grading required as soon as possible.
Sincerely Yours,
Wednesday, March 03, 1999 11:14:18 ,RESIDENTIAL DRAFTING SERVICE INC. Page 2 of 2
Ro C, V e i/(o
Draftsman, President
FAX COVER SHEET
Wednesday, March 03, 1999 11:23:53 AM
To: Lola M. Umbar
At: Rolling Hills Planning
Fax #: 13103777288
From: ROBERT DeMOSS
Company: RESIDENTIAL DRAFTING SERVICE INC.
Fax #: 562-420-3359
Voice: 562-421-0919
Fax: 1 page and a cover page.
Wednesday, March D3, 1999 11:23:53 .RESIDENTIAL DRAFTING SERVICE INC. Page 1 of 1
RESIDENTIAL DRAFTING SERVICE INC.
3706 Woodruff Ave. Long Beach, California, 90808 - 2123
Ph. (562) 421 - 0919 Fax. (562) 420 - 3359
March 3, 1999
Mrs. Lola M. Unbar
Planning Dept. City of Rolling Hills
# 2 Portuguese Bend Road
Rolling Hills, Calif. 90274
Ph. (310) 377 - 1521
Fax. (310) 377 - 7288
Subject: Bob Barth New Garage, Zone Case 585
Additional Grading Required per Soils Engineers Report.
Dear Lola;
At time of obtaining City of Rolling Hills approval for Garage, the existing Soil conditions where
unknown. Construction has not started, but we are in the process of obtaining required permits. Mr. Barth
obtained a Building Plan Check Extension, on September 16 th. to extend time to obtain permit until March
7 th. 1999. Due to Work overload, Residential Drafting Service Inc. has been behind in getting
Engineering and Plans revised for submittal. The Building plans have now been revised, regarding
Structural Engineering, and are in for Structural recheck at this time at the Lomita Office, Los Angeles
County Building Department.
The Soils Engineer, Western Laboratories of Torrance, California is requiring excavation of area at
proposed Four Car Garage from Four feet up to Eight Feet deep, than reuse soil and recompact for
Garage. To bring exterior grade up to within Six Inches of top of Foundation, and raise grade to provide a
level pad for Garage is going to require obtaining additional soil from site or possibly importing soil.
The Soils Report is requiring a minimum of Three Feet of Engineered, Compacted Soil under the required
Twenty Seven inch deep footing along with a earth key way at bottom of slope.
This is requiring us to submit Grading Plans plans to Los Angeles County Grading, Geology Division
for Grading Plan Check which we need to do this week. Our Los Angeles County Plan check expires March
7 th. but if the Grading Plans are in Plan check we have a Thirty Day Extension to April 6 th. to obtain
permits.
Seaboard Engineering is now preparing this Grading Plan, and will have complete this afternoon, and
I will deliver to you this afternoon. As the Grading Office is closed on Friday, I need to submit these grading
plans no latter than Thursday, March 4 at the Alhambra Office, County Building Dept. Grading Division.
According to the revised Grading Plan, this amounts to removing and recompacting approximately
202 Cubic Yards and obtaining from site or importing approximately 320 Cubic Yards of Soil, all to be
compacted per Soils Report for 2 : 1 Slope. Exposed slopes and area outside of Garage to be landscape to
control erosion. The original estimation of 15 Cubic Yards of removed and recompacted soil did not take in
account of Soils report, which we did not have that time.
Would appreciate your approval of extra grading required as soon as possible.
Sincerely Yours,
Draftsman, President
Western Laboratories
o
V 7 Geotechnical Engineering
February 26, 1999 Work Order 98-2556
MR. ROBERT BARTH
#29 Portuguese Bend Road
Rolling Hills, California 90274
Subject: Addendum No. 1
Geotechnical Engineering &
Engineering Geologic Investigation
Proposed Garage
# 29 Portuguese Bend Road
Rolling Hills, California
Dear Sir:
This addendum to our Geotechnical Engineering and Engineering Geologic Investigation,
dated July 15, 1998, Work Order 98-2556, is submitted.
The dimensions of the keyway to be excavated to support the proposed fill may be reduced
to a minimum width of twelve feet and a minimum depth of three feet into approved
bedrock, measured at the toe of the key.
We appreciate this opportunity to be of service to you.
Very truly yours,
WESTERN LABORATORIES
Kirk L. Sheller
Senior Engineer
R.C.E. 4683
741E
OF CO
3665 West 240th Street, Torrance, CA 90505 (310) 791-9001 — FAX (310) 791-0248
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
'MOM _N__o
--w IAia&10.MOft
IV IV
O V
Laboratories
Geotechnical Engineering
GEOTECHNICAL ENGINEERING
& ENGINEERING GEOLOGIC INVESTIGATION
PROPOSED GARAGE
#29 PORTUGUESE BEND ROAD
ROLLING HILLS, CALIFORNIA
JULY 15, 1998
WORK ORDER 98-2556
PREPARED FOR:
MR. ROBERT BARTH
#29 PORTUGUESE BEND ROAD
ROLLING HILLS, CALIFORNIA 90274
3665 West 240th Street, Torrance, CA 90505 (310) 791-9001 — FAX (310) 791-0248
1MM_ —
Western Laboratories
ws
T V
Geotechnical Engineering
July 15, 1998 Work Order 98-2556
MR. ROBERT BARTH
#29 Portuguese Bend Road
Rolling Hills, California 90274
Subject: Geotechnical Engineering &
Engineering Geologic Investigation
Proposed Garage
#29 Portuguese Bend Road
Rolling Hills, California
Dear Sir:
Pursuant to your authorization for geotechnical engineering and engineering geologic
consulting services, the accompanying report has been prepared.
Based upon the subsurface conditions that were encountered during our investigation, it is
our conclusion that the proposed garage is considered feasible from geotechnical engineering
and engineering geologic standpoints, provided the recommendations contained herein are
incorporated into the planning, design, and construction of the development.
The contents in this report should be reviewed in detail and be made a portion of the design
package. Please contact this office if any questions arise regarding the contents of this report.
Very truly yours,
WESTERN LABORATORIES
,itSSION4z
Kirk L. Sheller
Senior Engineer
R.C.E.
Ray,.. Eastman
C. G. 423
3665 West 240th Street, Torrance, CA 90505 (310) 791-9001 — FAX (310) 791-0248
Table of Contents
Introduction 4
Purpose and Scope of Work 4
Site Description 4
Field Exploration 5
Geologic Conditions 5
Groundwater 6
Seismic Conditions 6
Slope Stability 7
Conclusions 7
Recommendations 8
Notification of Governing Authorities 8
Site Grading and Compaction 8
Slope Construction 10
Utility Trenches 10
Spread Footing Foundations 11
Retaining Structures 12
Slabs -on -Grade 13
Site Surface Drainage 15
Closure 15
Supplemental Services 16
Maintenance 17
Selected References 17
Specifications for Compacted Fill 1 g
Appendix A - Test Pit Logs
Appendix B - Laboratory Testing
Appendix C- Geologic Maps & Cross Sections
Plot Plan
Western Laboratories
• • Geotecnnrcal Enarneenno
July 15, 1998 Work Order 98-2556
Introduction
This report presents the results of our geotechnical engineering and engineering geologic
investigation performed for the proposed garage to be constructed at #29 Portuguese Bend
Road, Rolling Hills, California.
The proposed development will entail construction of a one-story garage with exterior
masonry block or poured -in -place concrete walls combined with timber and stucco or
wooden siding, and a concrete slab -on -grade floor. A maximum anticipated foundation
loading of 2.5 kips/lin.ft. for continuous foundations was utilized for testing and design
purposes. If the actual design loading should exceed this value, this firm should be notified
in order that we may review, and if necessary, amend our recommendations.
Purpose and Scope of Work
The purpose of our exploration was to evaluate the soil conditions at the site and to provide
geotechnical engineering and engineering geologic recommendations for design and
construction of the proposed garage. Our work was based upon preliminary planning
information and was conducted in accordance with generally accepted practice for the
particular circumstance. The scope of our services included: review of selected geologic
maps; field geologic examination of the site; subsurface exploration by three exploratory test
pits; classification; laboratory testing; evaluation of the units encountered with respect to the
proposed development; and analyzing the results of the field and laboratory work to provide
the information contained in this report.
Site Description
The main residence site occupies approximately one thousand square feet that is situated at
the northerly flank of the Palos Verdes Hills. It is bounded on the southeast by Portuguese
Bend Road, on the northwest by a tributary to Spring Canyon, and in general by scattered
residential development.
Topography consists of two main aspects: a level parking area and a moderately steep,
northwesterly facing slope that is formed by the aforementioned canyon. The slope has an
approximate relief of approximately forty-five feet.
An overview of the site and topography is also shown on the accompanying base maps.
.._-
"il'aVWestern Laboratories
4
V Georecnnrcar Enarneenng
July 15, 1998 Work Order 98-2556
Field Exploration
The subsurface conditions at the site were explored by excavating three (3) twenty-four inch
wide exploratory test pits at the locations indicated on the attached Geologic Map. The test
pits were logged by an Engineering Geologist and disturbed and undisturbed samples were
obtained for laboratory testing and analysis.
Descriptions of the materials encountered in our test pits are presented on the logs in
Appendix A. The logs only depict subsurface conditions on the dates shown on the logs and
at the approximate locations shown on the Geologic Map. Subsurface conditions may differ
across the site from the conditions encountered in our test pits.
Bulk and relatively undisturbed soil samples were obtained at depths appropriate to the
exploration. The soil sampler utilized in our exploration included a 23/8-inch inside diameter
and 3'/4-inch outside diameter drive barrel, lined with numerous 1 inch brass rings. The
central portion of these ring samples were retained for testing. All samples were
immediately sealed in airtight containers and transported to the laboratory. Bulk, remolded,
and relatively undisturbed soil samples serve as the basis for the laboratory testing and
engineering conclusions contained in this report.
Geologic Conditions
The moderately rugged Peninsular Range comprises the geologic province and same extends
southeasterly from the Santa Monica and San Gabriel Mountains into Baja California. The
major geologic formations in the region include alluvium at the valley floors and
sedimentary, granitic and metamorphic bedrock in the mountainous terrain. Major fault lines
include the nearby Palos Verdes and Inglewood.
Geology at the site consists of three basic units, including: sedimentary bedrock, colluvium
and fill. The accompanying geologic maps, sections and logs present an overview.
The bedrock is assigned to the Altamira member of the Monterey Formation. It consists
mainly of firm, gray and brown, diatomaceous shale with interbeds of tan tuffaceous
sandstone, hard brown chert and gray brown marlstone. The tuffaceous sandstone is
dominant at this site and same is thickly and crudely bedded with dips of approximately 30
to 40 degrees toward the northwest.
The colluvium is present as a cover of approximately four feet on the bedrock. It consists
mainly of soft to stiff, dark brown, silty clay with rootlets.
"EST Western Laboratories
Iffur
V V Georecnnical Engineering
July 15, 1998 Work Order 98-2556
The fill occupies a surficial and localized wedge along the edge of the parking area. It is
anticipated to consist mainly of poorly compact, dark brown, silt and clay with rock
fragments.
Groundwater
Groundwater was not encountered in our exploratory test pits. Fluctuations in the
groundwater level at the site could occur due to variations in precipitation and numerous
other factors.
Seismic Conditions
The nearest active faults of significance to the site include the following:
Fault Zone
Palos Verdes
Inglewood
San Pedro Basin
Santa Monica
Whittier
Hollywood
Raymond
Approximate Location
2 miles north
8 miles northeast
14 miles southwest
20 miles northwest
22 miles northeast
22 miles north
25 miles northeast
(*) Maximum probable moment magnitude, CDMG 1996.
Earthquake Magnitude*
7.1
6.9
6.6
6.6
6.8
6.4
6.5
The associated ground motion parameters may be bracketed by the following:
Fault Zone
Palos Verdes
Inglewood
Whittier
(*) Seed 1983
Western Laboratories
Anticipated Horizontal
Acceleration -Peak (g)*
0.60
0.37
0.16
6
Anticipated Horizontal
Acceleration-65% Peak(g)*
0.39
0.24
0.10
♦ ♦ udctec^nrc ,
July 15, 1998
Work Order 98-2556
The accompanying fault and earthquake epicenter maps present an overview.
Slope Stability
Slope stability analyses were performed utilizing cross section A. The slope stability
analyses were performed using TENSLO1, a slope stability program that uses Bishop's
Modified method of Analysis. The resulting factors of safety exceeded the commonly
accepted engineering standards of 1.5 for static conditions and 1.1 for pseudostatic
conditions at all evaluated tangent depths. Calculations and cross sections are provided in
Appendix C.
A surficial slope stability analysis was performed for the near surface soils along the
descending slope face. The resulting factors of safety exceeded the commonly accepted
engineering standards of 1.5 for static conditions and 1.1 for pseudostatic conditions.
Calculations and cross sections are provided in Appendix C. It should be realized that even
though the factors of safety were satisfactory; surficial sloughing may occur.
Conclusions
The proposed development is considered feasible from geotechnical engineering and
engineering geologic standpoints, subject to the conclusions and recommendations that
follow.
The site is grossly stable in as much as landslides or active faults are not known to be
present. Moreover, the site topography and firm, thickly bedded and steeper than natural
slope dip characteristics of the bedrock are favorable for gross stability. Fills and colluvium
situated on the slope areas are typically subject to sloughing and down slope creep.
Nearby active fault lines include the Palos Verdes and Inglewood. These have associated.
postulated maximum probable earthquake magnitudes of 6.9-7.1. The related. repeatable
ground motion accelerations range upwards to approximately 0.39g.
In accordance with Section 111, the proposed construction will be safe from a geotechnical
engineering and engineering geologic standpoint against hazard from landsliding, settlement
or slippage. The proposed construction and grading operations will not have an adverse
effect on the project site or adjacent properties, provided the work is performed according
to the recommendations of this office.
Total and differential foundation settlements should be on the order of one-half inch and one -
quarter inch, respectively.
1:-.1117Western Laboratories
ww
♦ .
Geotecnntcal Engineering
July 15, 1998 Work Order 98-2556
Detailed recommendations to be utilized in the design and construction of the proposed
development are presented in the following sections of this report.
Recommendations
The recommendations provided in this report are based upon observations made in the field,
the results of laboratory tests on samples of the materials encountered during the subsurface
exploration, and the past experience of this office.
Notification of Governing Authorities
Site grading operations should be performed in accordance with the local building and safety
codes and the rules and regulations of those governmental agencies having jurisdiction over
the subject construction.
A pre -grade meeting should be conducted with the owner's representative, the grading
contractor, the grading inspector, and the Soils Engineer prior to initiating grading
operations.
The grading contractor is responsible to notify the required governmental agencies and the
Soils Engineer prior to initiating grading operations, and any time grading is resumed after
an interruption.
Site Grading and Compaction
All vegetation and the upper few inches of soils containing organic matter should be stripped
and hauled from the proposed fill areas prior to the start of the grading operations. Utility
lines to be abandoned should be excavated and removed from the site.
The fill soils and colluvium are not suitable in their present condition for slab, structural, or
pavement support. These units should be excavated to approved bedrock, which should be
observed and approved by the Soils Engineer and Engineering Geologist. The proposed fill
should be supported by a keyway excavated at the toe of the proposed fill, having a minimum
width of fifteen feet and excavated to a minimum depth of 5.0 feet into approved bedrock,
measured at the toe of the key.
Western Laboratories
ww
3ec;eCni71car E.mmneenng
July 15, 1998 Work Order 98-2556
A subdrain should be placed at the heel of the key to accommodate drainage. The proposed
subdrain should be constructed of a minimum 4-inch diameter PVC Schedule 40 or ABS
Class SDR 35 pipe. The pipe should have a minimum of 8 uniformly spaced perforations
per foot of pipe installed, with perforations pointing downward. A cap should be provided
at the upstream end of the pipe, and a minimum slope of 2 percent should be provided to the
outlet pipe. A 4-inch diameter non -perforated outlet pipe should carry the collected water
to the face of the slope. The outlets should be spaced at a minimum of 100 foot intervals
measured horizontally, and should extend 12 inches beyond the face of the slope at the time
of rough grading. The effluent should be carried from the face of the slope by a non -
perforated pipe or drainage swail to an appropriate discharge point. The perforated pipe
should be encased within a filter material, having a minimum sand equivalent of 50, a
minimum of one cubic foot per foot of pipe. The filter material should be wrapped in filter
fabric, Mirafi 140NL or equivalent.
As the grading operation proceeds, the exposed bedrock should be benched to create a level
surface to receive compacted fill soils. Proposed fill soils should be cleansed of any root
structures and deleterious debris, and be brought to proper moisture content. Fill soils should
be spread in 8-inch thick loose lifts, moisture conditioned as required, and compacted to at
least 90 percent relative compaction, in accordance with the "Specifications for Compacted
Fill Soils". Successive layers of fill should be continually benched into undisturbed soil or
bedrock.
A keyway will not be required if a retaining wall supports the downslope edge of the
proposed fill; however, benching, compaction and draining of the retained soil will be
required.
Foundations should not transition from a condition where they are underlain by bedrock to
one where they are underlain by engineered fill soils (cut/fill transition). If this will occur,
the entire building pad extending a minimum horizontal distance of five feet outside of
perimeter foundations should be overexcavated to a minimum depth of three feet beneath
proposed foundations.
Concrete slabs -on -grade and pavement located outside of the building pad and located in
areas having cut/fill transitions should be underlain by a minimum of two feet of compacted
fill soils. This overexcavation should be accomplished by excavating to a minimum depth
of 1.0 foot beneath the bottom of the proposed pad elevation or to approved bedrock,
whichever is deeper. The exposed native subgrade should be processed to a minimum depth
of 12 inches and compacted to a minimum of 90 percent of ASTM D 1557-91. The
excavated soils should then be replaced in 8-inch thick loose lifts, moisture conditioned as
required, and compacted to a minimum of 90 percent of ASTM D 1557-91.
Western Laboratories
v Geotechnrcal Engineering
9
July 15, 1998 Work Order 98-2556
Unstable subsurface conditions are frequently encountered when grading operations are
conducted when the ground is wet. If areas of unstable subgrade are encountered during
grading operations, stabilization will be required prior to placement of fill soils, construction
of slabs, foundations, or roadways. These areas are best evaluated for appropriate
stabilization during the grading operation.
Any proposed import fill soils should be approved by the Soils Engineer prior to importing
to the site. Any additional fill soils placed should also be compacted in accordance with the
attached "Specifications".
Slope Construction
Any temporary excavation without shoring should be cut at a maximum slope of 1:1 (1
horizontal to 1 vertical), to a maximum height measured vertically of 15.0 feet. A visual
inspection should be performed during the excavation by a representative of this firm.
Temporary construction cut slopes are suitable for a short time duration, not to exceed six
weeks.
In areas where a temporary 1:1 slope is not feasible, shoring designed by a Registered
Professional Engineer knowledgeable and qualified in shoring design should be provided to
support adjacent soils, structures, streets, and appurtenances, and to safeguard personnel.
Permanent cut and fill slopes should be no steeper than 2:1 (2 horizontal to 1 vertical). In
areas where steeper grade changes are desired, retaining walls should be utilized to
accommodate the recommended slope gradient. Slopes should be planted with fast-growing,
deep-rooted ground cover to reduce sloughing and erosion.
Utility Trenches
Backfill of utilities within right-of-ways should be placed in strict conformance with the
requirements of the governing agencies.
Following placement of utility lines within private property, the space under and around the
line should be backfilled with clean sand or approved granular soil to one foot over the pipe.
The sand backfill should be uniformly jetted into place before the remainder of the backfill
is placed over the sand.
All backfills over the bedding material should be mechanically compacted to at least 90
percent of the maximum density obtainable by the ASTM D 1557-91 method. Jetting or
flooding of the backfill over the bedding should not be permitted.
WY' Western Laboratories
- 1 0 -
V Geotecnnicai Enci^eennq
July 15, 1998 Work Order 98-2556
Utility trench backfills should be observed and tested during backfill operations as the work
progresses. If the testing of a backfill is performed after completion, without observing the
backfill operations, then only the test results at the test locations can be given.
Spread Footing Foundations
Following completion of the bulk grading operation and compaction testing, the proposed
garage should be supported on conventional foundations excavated to a minimum width of
12 inches and a minimum depth of 27 inches below lowest adjacent grade, into engineered
fill soils. Continuous foundations having the preceding dimensions and founded into
engineered fill soils should be designed utilizing an allowable bearing pressure of 1700
pounds per square foot (psf).
Resistance to lateral loadings may be provided by friction acting on the base of foundations
that are in contact with the engineered fill soils. A coefficients of friction of 0.25 may be
applied to dead load forces. Passive earth pressure should be computed as an equivalent
fluid of 200 pounds per cubic foot (pcf), to a maximum value of 2000 psf, for the portion of
the foundations that are founded into engineered fill soils.
As an alternative to excavating foundations into the engineered fill soils, the proposed garage
should be supported on conventional foundations excavated to a minimum width of 12
inches and a minimum depth of 27 inches below lowest adjacent grade, of which a minimum
of 12 inches should be excavated into approved bedrock. Continuous foundations having
the preceding dimensions and founded into approved bedrock should be designed utilizing
an allowable bearing pressure of 3000 pounds per square foot (psf).
Resistance to lateral loadings may be provided by friction acting on the base of foundations
that are in contact with approved bedrock. A coefficient of friction of 0.35 may be applied
to dead load forces. Passive earth pressure should be computed as an equivalent fluid of 350
pounds per cubic foot (pcf), to a maximum value of 3500 psf, for the portion of the
foundations that are founded into approved bedrock.
The allowable soil pressures may be increased one-third for combinations of vertical and
horizontal forces where permitted by the Uniform Building Code.
Foundations should be stepped as necessary to produce level tops and bottoms. Foundations
should be deepened to provide a minimum of H/3 feet of horizontal confinement between
the bottom of the foundation and the face of the nearest slope. We recommend that the
minimum setback should be 10.0 feet, and need not exceed 40.0 feet.
- 11 -
Western Laboratories
V V Gectecnnical Engmeenng
July 15, 1998 Work Order 98-2556
Foundations constructed adjacent to utility lines should be excavated to a depth so that its
surcharge, extending at a one horizontal to one vertical projection (1:1) down from the
bottom of the foundation, will not impact the utility line.
Continuous foundations should be reinforced with a minimum of one #5 Bar, top and
bottom. A continuous foundation system is recommended throughout the structure.
Foundation excavations should be observed by the Soils Engineer prior to the placement of
reinforcing steel to verify uniform soil conditions and conformance with the
recommendations in this report.
Retaining Structures
Retaining structures constructed at the site should be designed to resist active lateral earth
pressures plus surcharge loadings resulting from loads acting on the retention portion, of the
structure. Retaining structures should be designed to resist equivalent fluid pressures
presented in the following table.
Surface Slope of Equivalent
Retained Material Fluid Density
(Horizontal to Vertical) (Lbs./Cu.Ft.)
Level 45
2 to 1 60
Retaining walls that are restrained from horizontal movement at the top should be designed
using an equivalent fluid pressure of 65 pcf.
Retaining walls should be supported on spread footing foundations designed in conformance
with the recommendations presented in the preceding portions of this report. Retaining walls
should be designed to have a minimum factor of safety of 1.5 in resisting sliding and
overturning.
Retaining walls should be backdrained to collect accumulated moisture and prevent
hydrostatic pressures from accumulating. A 4-inch diameter rigid perforated drain line. PVC
Schedule 40 or ABS with SDR of 35 or better, encased in a minimum of 1 cu.ft./ft. of clean,
free -draining crushed rock or gravel, should be placed at the base of the stem wall to collect
any accumulated moisture. The pipe should be sloped to drain to appropriate receptacles by
gravity.
- 12-
Western Laboratories
V V Gectecnnrcat Enatneerrnc
July 15, 1998 Work Order 98-2556
The crushed rock should be wrapped in filter fabric (i.e. Mirafi 140NL or equivalent). The
remainder of the backfill should be comprised of a clean sand, having a minimum width of
1.0 foot on top of the gravel and filter fabric extending vertically to within two feet of
proposed final grade. The remaining two feet of the backfill should be comprised of fill
material compacted in accordance with the grading recommendations.
In areas where moisture migration through retaining walls undesirable, retaining walls should
be waterproofed.
Retaining walls should be backfilled prior to building on or adjacent to the walls as the walls
will yield slightly during backfilling.
Slabs -on -Grade
Building area concrete slabs -on -grade constructed upon engineered fill soils should be a
minimum of 5 inches thick. The slabs should be reinforced with a minimum of #5 Bars,
placed 18 inches on center in both directions and positioned in the center of the slab. The
reinforcement should be supported upon concrete dobies in order to ensure proper
positioning during concrete placement. Diagonal reinforcing bars should be placed at all re-
entrant comers to keep cracks from opening excessively. Two #3 bars about 2 feet 6 inches
long should be located about 2 inches and 5 inches from each comer in the center of the slab.
Slabs should be structurally tied to perimeter foundations, utilizing bar ties that match the
slab reinforcement and wrap around foundation reinforcement. The bar ties should extend
a minimum distance of 3.0 feet into the slabs. -
In building areas where moisture intrusion through the slab is undesirable, the slabs should
be underlain with a capillary moisture break consisting of a minimum of 4 inches of clean,
free -draining crushed rock or gravel, with a minimum dimension of /4 inch and a maximum
dimension of 3/4 inch. An impermeable membrane moisture vapor barrier (6 mil
polyethylene or equivalent) should be utilized between the capillary moisture break and slabs
where migration of moisture vapor through slabs would be detrimental. The membrane
should be encased within a minimum of 2 inches of sand to protect it during construction.
The expansion potential of the subgrade soils should be reduced by moisture conditioning
the subgrade to 140 percent of optimum moisture content to a depth of 33 inches.
The contractor should be responsible for supplying the concrete mix design for the slab to
the owner. A pea gravel pump mix is not recommended. The contractor should use a well
graded conventional crush rock aggregate mix (i.e. 1-inch maximum aggregate size).
Western Laboratories
-13-
V V Geotechnical Engineering
July 15, 1998 Work Order 98-2556
Joints should be utilized within the slab to induce and control cracking. Control joints
should be spaced a maximum distance of 15 feet in each direction. Control joints should be
cut to a depth equivalent to one -quarter of the thickness of the slab. Joints made with a
power blade are usually cut within 4 to 12 hours after the slab has been placed and finished.
Joints must be cut as soon as the concrete surface is firm enough not to be torn or damaged
by the blade, and before random shrinkage cracks can form in the concrete slab. Joints for
sidewalks should be spaced at intervals equal to the width of the sidewalk.
The concrete contractor should provide concrete designs and should place, finish, and cure
concrete in accordance with ACI recommended practices.
These minimum concrete thickness and reinforcement recommendations are based upon the
expansion potential of the on -site soils only. The Structural Engineer for the project may
need to address other factors which may require modification of the preceding
recommendations.
The following recommendations are provided with the intent of reducing the risk of
substantial differential movement and cracking of exterior concrete slabs -on -grade, and
supplement the previous recommendations for slabs -on -grade.
Exterior slabs that are immediately adjacent to the proposed structure should be structurally
continuous with the proposed structure, or a separation should be provided. In order to
minimize the potential for differential movement of the outer edge of the concrete slabs -on -
grade, cut-off walls should be provided having a minimum width of 8 inches and a minimum
depth of 24 inches below lowest adjacent grade.
Cut-off walls should be reinforced with a minimum of one #5 Bar, top and bottom. The
slabs should be structurally tied to perimeter foundations by bar ties matching slab
reinforcement that wrap around foundation reinforcement and extend a minimum of 3.0 feet
into slabs.
The expansion potential of the subgrade soils should be reduced by moisture conditioning
the subgrade to 140 percent of optimum moisture content to a depth of 33 inches.
A 4-inch thick layer of Class 2 aggregate base material should then be spread, moisture -
conditioned as necessary, and compacted to at least 95 percent relative compaction. The
aggregate base material should also be smooth and nonyielding.
- 14-
Western Laboratories
v Geotecnn;cai Engmeenng
July 15, 1998 Work Order 98-2556
Exterior concrete slabs -on -grade should be a minimum of 5 inches thick. The slabs should
be reinforced with a minimum of #5 Bars, placed 18 inches on center in both directions and
positioned in the center of the slab. The reinforcement should be supported upon concrete
dobies in order to ensure proper positioning during concrete placement. Concrete sections
that are to be stamped should be a minimum of 6 inches thick.
A minimum of 2 inches of concrete cover should be maintained from the surface of the slab
or from the bottom of the stamped depth to the reinforcement.
Site Surface Drainage
Surface water should be diverted away from slopes and foundations. Roofs should be
provided with gutters, and the downspouts should be connected to appropriate receptacles.
Roof downspouts and surface drains should be maintained entirely separate from retaining
wall backdrains. The outlets should discharge into erosion -resistant areas, and should be
provided with rock rip -rap or other energy dissipaters, if they discharge onto the ground.
Planters adjacent to building areas, driveways, and concrete flatwork areas, should be
properly sealed to prevent the intrusion of moisture into these areas. The excess irrigation
water from the planter should be collected in a drain or be allowed to spill over the top of the
planter in areas where ample sheet drainage is available to disperse it.
Closure
This report is prepared for the specific use of Mr. Robert Barth for development of the
proposed project described herein. Findings in this report are valid as of this date; however,
changes in conditions of a property can occur due to the passage of time, whether they are
due to natural processes or works of man, on this or adjacent properties. In addition, changes
in applicable or appropriate standards occur whether they result from legislation or
broadening of knowledge. Accordingly, findings of this report may be invalidated wholly
or partially by changes outside our control. Therefore, this report is subject to review after
a period of one year.
Western Laboratories
ww
v v Geotechrncal Enomeernno
- 15 -
1
1
July 15, 1998
Work Order 98-2556
Our services consist of professional opinions and conclusions developed by an Engineering
Geologist and a Professional Engineer specializing in the field of soil mechanics. The
warranty or guarantee made by the consultants in connection with the services performed for
this project is that such services are performed with the care and skill ordinarily exercised
by members of the same profession practicing under similar conditions at the same time and
in the same or a similar locality. No other guarantee or warranty, either express or implied,
is made or attempted by rendition of consulting services, or by furnishing written reports of
the findings.
The information and recommendations of this report are based upon the assumption that the
soil conditions do not deviate from those disclosed in the explorations. If any variations or
undesirable conditions are encountered during construction, or if the proposed construction
will differ from that planned at the present time, Western Laboratories should be notified so
that supplemental recommendations may be provided.
This report is issued with the understanding that it is the responsibility of the owner or of his
representative, to ensure that the information and recommendations contained herein are
called to the attention of the Architect and Engineers for the project and incorporated into the
plans and that the necessary steps are taken to see that the Contractors and Subcontractors
carry out such recommendations in the field.
This report is subject to review by the controlling authorities for the project.
Our scope of work did not include evaluation of potential hazardous material contamination
of soil or groundwater.
Supplemental Services
We should review the final plans for conformance with the intent of our recommendations.
During construction, we should observe the conditions encountered in construction
excavations and modify our recommendations, if warranted.
We should observe footing excavations prior to placement of forms or reinforcement. We
should verify that the subgrade soils beneath concrete slabs -on -grade are moisture
conditioned a maximum of 48 hours prior to placement of visqueen over the subgrade. Our
services during foundation construction are limited to observation of soil conditions, depth
of excavation, and the condition of excavations prior to placement of reinforcement. Our
services do not include observation or approval of steel, concrete, or asphalt; nor do they
include establishing or verifying construction lines and grades. This should be performed
by the appropriate party. We should summarize the results of this work in a final report.
We Western Laboratories
IN/ 1M
- 16-
Geotecnn,c3l Engineering
July 15, 1998 Work Order 98-2556
These supplemental services are performed on an as -requested basis, and we cannot accept
responsibility for items that we are not notified to observe. These supplemental services are
in addition to this geotechnical engineering report, and are charged for on an hourly basis in
accordance with our Professional Fee Schedule.
Maintenance
Periodic land maintenance will be required. Surface and subsurface drainage facilities
should be checked frequently, and cleaned and maintained as necessary.
Selected References
Probabilistic Seismic Hazard Assessment, California Division of Mines and Geology, 1996,
OFR 96-08; Ground Motions and Soil Liquefaction During Earthquakes, H. B. Seed, 1983,
Earthquake Engineering Research Institute; Map Showing Late Quaternary Faults of the Los
Angeles Region, U.S. Geologic Survey, 1989, MF-1964; Evaluating Earthquake Hazards in
the Los Angeles Region, U.S. Geological Survey, 1985, Professional Paper 1360; Geologic
Map of the Palos Verdes Hills, U.S. Geological Survey, 1946, Professional Paper 207.
-17-
=_. Western Laboratories
V V Geotecnn,cal Engmeenna
1
1
1
July 15, 1998 Work Order 98-2556
Specifications for Compacted Fill
Preparation
The existing fill should be removed under the observation of the Soils Engineer to expose
subgrade competent to support the engineered fill. After the foundation for the engineered
fill has been exposed, it shall be scarified until it is uniform and free from large clods,
moisture conditioned where necessary and compacted, as specified in the body of this report,
in accordance with ASTM D 1557-91 (5 layers - 25 blows per layer; 10 lb. hammer - 18 inch
drop).
Materials
On -site soils may be used for the fill, or imported fill materials shall consist of materials
approved by the Soils Engineer, and may be obtained from the excavation of banks, borrow
pits or any other approved source. The materials used should be free of vegetable matter and
other deleterious substances and should not contain rocks or lumps greater than four inches
in maximum dimension.
Placing. Spreading and Compacting Fill Materials
A. The selected fill material should be placed in layers which when compacted shall not
exceed six inches in thickness. Each layer should be spread evenly and thoroughly mixed
during the spreading to attain uniformity of material and moisture of each layer.
B. Where the moisture content of the fill material is below the limits specified by the Soils
Engineer, water should be added until the moisture content is satisfactory to attain thorough
bonding and thorough compaction.
C. Where the moisture content of the fill material is above satisfactory limits, the fill
materials should be aerated, blended or dried by other methods until the moisture content is
satisfactory.
D. After each layer has been placed, mixed and spread evenly it should be compacted, as
specified in the body of this report, in accordance with ASTM D 1557-91 (5 layers - 25
blows per layer; 10 lb. hammer - 18 inch drop) or other density tests which will attain
equivalent results.
Compaction should be by sheepsfoot roller, multi -wheel pneumatic tire roller or other types
of acceptable rollers. Compaction equipment should be of such design that they will be able
to compact the fill to the specified density.
Western Laboratories
v v Geotecnnicai Enorneenna
- 18-
July 15, 1998 Work Order 98-2556
Compaction should be accomplished while the fill material moisture content is within the
compactable range. Compaction of each layer should be accomplished by covering the entire
area and the roller should make sufficient trips to attain desired density. The final surface
of the lot areas to receive slabs -on -grade should be rolled to a dense, smooth surface.
E. The outside of all fill slopes should be compacted by means of sheepsfoot rollers or other
suitable equipment. Compaction operations should be continued until the outer face of the
slope is compacted to a minimum of 90% relative compaction. Compacting of the slopes
should be done progressively in increments not to exceed 4.0 feet as the fill is brought to
grade.
F. Field density tests should be made by the Soils Engineer of the compaction of each layer
of fill. Density tests should be made at intervals not to exceed two feet of fill height provided
all layers are tested. Where the sheepsfoot rollers are used, the soils may be disturbed to a
depth of several inches and density readings should be taken in the compacted material below
the disturbed surface. When these readings indicate the density of any layer of fill or portion
thereof is below the required density, the particular layer or portion should be reworked until
the required density has been obtained.
Observation
Observation by the Soils Engineer should be made during all filling and compacting
operations so that he can verify that the engineered fill was consistent, competent and in
compliance with the recommendations.
Seasonal Limitations
No fill materials should be placed, spread or rolled during unfavorable weather conditions.
When work is interrupted by heavy rains, fill operations should not be resumed until the field
tests by the Soils Engineer indicate that the moisture content and density of the fill are as
previously specified.
-19-
ww
Western Laboratories
Geotecnnical En vneenng
APPENDIX A
TEST PIT LOGS
•
Western Laboratories
ww
V V Georecr.nrcai Engineenng
Sample Type:
Laboratory Tests:
LEGEND
R = Relatively Undisturbed Ring Sample
B = Disturbed Bag Sample
NR = No Recovery
SP = Standard Penetration Test
DS = Direct Shear Test
CN = Consolidation Test
El = Expansion Index
EX = Expansion Index Test
PI = Plasiticity Index Test
LL = Liquid Limit
PL = Plastic Limit
RV = Resistance Value
UC = Unconfined Compression Test
Western Laboratories
ww
v v Geotecnnical Engineering
Client:
Project:
TEST PIT 1
MR. ROBERT BARTH
PROPOSED GARAGE
en .
TEST PIT LOG 3 3
4-4U
C
�.1 y
= a F
E a o A
CZ Extension Backhoe w/24" Wide Bucket
0 0.0- 1.0' COLLUVIUM-Silty CLAY(CH)w/rootlets-
1.0- 3.5' Dk.Brown, soft, moist
B COLLUVIUM-Silty CLAY(CH)w/rootlets-
Dk.Brown, stiff, moist
3.5- 6.0' ALTAMIRA-Tuffaceous Fine SAND-
5 STONE -Tan, dense, moist - crudely bedded
6.0' l at N75E30N
Hard Brown Cemented Tuff - Refusal
Test Pit Halted and Backfilled
No Groundwater Encountered
10
15
20
25
30
Western Laboratories
v v Geotecnnicai Encineenna
W.O. 98-2556
Date: 5-1-98
22.7
Client:
Project:
TEST PIT 2
MR. ROBERT BARTH
PROPOSED GARAGE
W.O. 98-2556
Date: 5-1-98
s e
ao i
TEST PIT LOG 'r. w °''
.- � � co
:U wo
a F. . rt"7 0
CI cn .4 m Extension Backhoe w/24" Wide Bucket
0 0.0- 1.0' COLLUVIUM-Silty CLAY(CH)w/rootlets-
1.0- 2.5' ! Dk.Brown, soft, moist
R DS COLLUVIUM-Silty CLAY(CH)w/rootlets- 82.4 26.5
2.5- 6.0' 1 Dk.Brown, stiff, moist
_ B EX ALTAMIRA-Tuffaceous Fine SAND- 16.6 E1=23
5 R DS STONE -Massive, Tan, dense, moist 102.5 15.2
6.0' )-Contact at N80W3ON
Hard Brown Cemented Tuff - Refusal
Test Pit Halted and Backfilled
No Groundwater Encountered
10
15
20
25
30
__.Western Laboratories
ww
V V Geotechn:cal Engineering
Client:
Project:
TEST PIT 3
MR. ROBERT BARTH
PROPOSED GARAGE
W.O. 98-2556
Date: 5-1-98
w ...
TEST PIT LOG 1
3 0
U z
:U 6) I. c
= 1w
Z
i� H A
✓ a F 3 t.'-] c o
c ▪ v o• o
Extension Backhoe w/24" Wide Bucket
0 0.0- 1.0' COLLUVIUM-Silty CLAY(CH)w/rootlets-
1.0- 4.0' 1 Dk.Brown, soft, moist
B COLLUVIUM-Silty CLAY(CH)w/rootlets- 24.5 EI=105
_. Dk.Brown, stiff, moist
_ 4.0- 7.5' ALTAMIRA-Tuffaceous Fine SAND-
5 STONE -Massive, Tan, dense, moist
B - irregular 2" Gray Bentonite lense at 6' 40.2
10
15
20
25
30
Western Laboratories
ww
Y Y Geotechnical Enaineenno
Test Pit Halted and Backfilled
No Groundwater Encountered
APPENDIX B•
LABORATORY TESTING
c Western Laboratories
INF ‘Ill
V Geatechncal Engrneenna
t
1
1
1
1
1
1
1
i
1
1
1
1
Now
Laboratory Testing
The natural water content and dry density were determined on selected samples of the
materials recovered from the test pits. This information is recorded on the test pit logs at the
appropriate sample depths.
Direct Shear Tests (ASTM D 3080) were performed with a strain control type shear machine
where the soil samples are subjected to a 0.002 inch per minute rate of strain, under varying
loads and under conditions of saturation.
Expansion Index Tests were performed on representative samples of the near surface soils
in accordance with UBC 29-2. In this test, soil is compacted into a metal ring to ±50 percent
saturation. The sample is then placed in a device producing confining pressure of 144 psf
(1 psi). The sample is then inundated with water and the amount of swell expressed as a
ratio of the initial sample height times 1000 is recorded as the Expansion Index. The results
of these tests indicate the soils to be medium to high in expansion potential, according to the
preceding standard.
c Western Laboratories
15,11.
1 .
Geotecrnicai Enaineenna
(ASTM D 3080)
4.0 4.0
3.0
1.0
0.0
0.0 1.0 2 0 3.0
Normal S ress (psf)
Thousands
TP-2 AT 2.0 FEET
Angle of internal friction =
Cohesion =
RA2 =
17.9 deg
560 psf
0.957
(75
t6
N
0)
3.0
1.0
0.0
0.0 1.0 2.0 3.0 4.0
4.0 Normal Stress (psf)
Thousands
`TP-2 AT 2.0 FEET
* Residual
13.0 deg
265 psf
0.963
PROJECT: PROPOSED GARAGE WORK ORDER 98-2556
DIRECT SHEAR TEST
Western Laboratories
7 V Geotechnrcal Engrneerrng
4.0
3.0
1.0
0.0
(ASTM D 3080)
0.0 1.0 2.0 3.0 4.0
Normal Stress (psf)
Thousands
TP-2 AT 5.0 FEET
Angle of internal friction =
Cohesion =
RA2 =
38.5 deg
635 psf
0.997
4.0
3.0
2.0
1.0
0.0
0.0 1.0 2.0 3.0 4.0
Normal Stress (psf)
Thousands
`TP-2 AT 5.0 FEET
Residual
33.0 deg
370 psf
0.999
PROJECT: PROPOSED GARAGE WORK ORDER 98-2556
DIRECT SHEAR TEST
Western Laboratories
v v Geotechnical Engineering
APPENDIX C
SLOPE STABILITY,
GEOLOGIC MAPS &
CROSS SECTIONS
Western Laboratories
ww
• • Geotechnica! Engineering
me an on is ea an sum Eli I• owe i i me no am me no um um
Ueritcal height
140 -
120 -
80-
60-
r
'TENSLOPE' Geometry Plot
Title: PROPOSED GARAGE Soil Gamma CBAR Phi C ( 86.75 86.25 )
Project: #29 PORTUGUESE BEND 1 0.120 0.265 13.0 R=54.25 FS= 2.29
2 0.120 0.370 33.0
Case: SECTION A (STATIC))
Date: O7/ 15i98
1
2
1 1 1 1 i 1 1 1
20 40 60 80 100 120 140 160 180
Horizontal distance (feet)
am an — — 0 an an lei ,inui um r an an i on m ,am
'CONTOUR' Data Plot
88-
87 — +
2.29
L
a, +4-
ry 2.29
t. 2.29 2.29
o� 86— + + + + +
• P. 2.29 2.29 2.29 2.29 2.29
t
rp
U
L
co
85 — +
2.30
+
2.30
+ +
2.29 2.30
1 1 I 1 I
86 87 88 89 90
Horizontal distance (meters)
Tenslope, version Tenslope V1 - (c) 1986-1991
Slope stability by the modified Bishop method.
Program by the Tensar Corporation, April 1986.
Title: PROPOSED GARAGE
Project: #29 PORTUGUESE BEND
Case: SECTION A (STATIC) )
Date: 07/15/98
"Units: Kips/ft
Rapid drawdown indicator: No (def)
J
Seimic forces: No
Horizontal acceleration: 0.15
* Seismic forces acting at: Center
Soil
No.
I
2
l
Point data:
No. X-coord.
1 0.00
2 69.50
3 121.00
4 142.50
5 156.00
6 174.00
7 0.00
8 69.50
9 121.00
10 174.00
I Line
No.
1
2
3
4
5
6
7
8
information:
GAMMA CBAR
0.120 0.265
0.120 0.370
Phi
13.0
33.0
Y-coord.
45.50
31.00
55.00
55.00
61.50
61.50
43.00
29.00
53.00
55.50
array:
Left X Y
* 1 0.00 45.50
2 69.50 31.00
3 121.00 55.00
4 142.50 55.00
5 156.00 61.50
* 7 0.00 43.00
8 69.50 29.00
9 121.00 53.00
RU
Phreatic
Phreatic
Right X Y
2 69.50 31.00
3 121.00 55.00
4 142.50 55.00
5 156.00 61.50
* 6 174.00 61.50
8 69.50 29.00
9 121.00 53.00
* 10 174.00 55.50
,Phreatic surface coordinates:
No. X-coord. Y-coord.
1 0.00 32.50
2 69.50 29.00
3 121.00 53.00
4 174.00 55.50
"Unit weight of fluid = 0.0624
riezometric surface coordinates for soil A:
No. X-coord. Y-coord.
111 1 .00 .00
Mu
0.00
0.00
Angle
-11.78
24.99
0.00
25.71
0.00
-11.39
24.99
2.70
by the Tensar Corporatio
Soil Topline
1 Yes
1 Yes
1 Yes
1 Yes
1 Yes
2 No
2 No
2 No
"Stone columns: No
Stone column zones: (porosity = 0.000 )
1/ Zone Col Dia Spacing CBAR Phi Gamma Stress ratio
* 1 .0 ..0 .000 .000 .000 .00
"Limits of stone columns:
* Zone X-left X-right Y-top Y-bottom
II 1 .00 .00 .00 .00
Tensar geogrid placement:
' Layer Elev. X-left X-right
1 .00 .00 .00
Tensar geogrid strength data:
I Layer Geogrid Ult Strength Percent Design FS-Pull Percent
type Kips/ftll Ult Strength out Coverage
1 .000 .000 %%.%%% .00 .00
IIGeogrid forces derated: No
* Derating constant of grid: 1.10
,Option: Search
* Grid point X-coord Y-coord
)1 1 .00 .00
2 .00 .00
3 .00 .00
il
1-2 .00
2-3 .00
Automatic search for critical circle:
,Initial X = 87.00 feet 44 Initial Y = 85.00 feet 44
Delta X = 1.00 feet 44 Delta Y = 1.00 feet 44
,Approximately 20 slices will be used at RMAX
Minimum tangent elevation for any failure circle is 32.00 feet 44
Maximum tangent elevation for any failure -circle is 50.00 feet 44
There are 18 increments between tangent levels
IIIII N S r— N N NM r ■r — r r MI NM G MI
'TENSLOPE' Geometry Plot
140 -
120 -
a
w 100-
Title: PROPOSED GARAGE soil Gamma CBRR Phi C ( 86.75 99.25 )
Project: #29 PORTUGUESE BEND 1 0.120 0.265 13.0 R=67.25 FS= 1.61
2 0.120 0.370 33.0
Case: SECTION A (SEISMIC)
Date: 07/15/98
1
I I I I I I I I
20 40 60 80 100 120 140 160 180
Horizontal distance (feet)
— M M '— r 'r i„ /`11111i r M M— M r 10111
u• l
L
cu
aJ
'CONTOUR' Data Plot
101 -
100- +
1.61
.+.
1.61
+ +
1.61 1.61
o 99- + + + + +
1.61 1.61 1.61 1.61 1.61
a
r
1
rp
u
L
a
98 - +
1.61
1.61
1 1 1 1 I
86 87 88 89 90
Horizontal distance (meters)
1
Tenslope, version Tenslope V1 - (c) 1986-1991
Slope stability by the modified Bishop method.
Program by the Tensar Corporation, April 1986.
Title:
Project:
Case:
Date:
PROPOSED GARAGE
#29 PORTUGUESE BEND
SECTION A (SEISMIC)
07/15/98
Units: Kips/ft
Rapid drawdown indicator: No (def)
IISeimic forces: Yes
Horizontal acceleration: 0.15
Seismic forces acting at: Center
1 Soil
No.
1
2
Point
1N0.
1
2
3
5
6
7
8
9
10
Line
INo.
1
2
3
5
6
7
information:
GAMMA CBAR
0.120 0.265
0.120 0.370
data:
X-coord.
0.00
69.50
121.00
142.50
156.00
174.00
0.00
69.50
121.00
174.00
Phi
13.0
33.0
Y-coord.
45.50
31.00
55.00
55.00
61.50
61.50
43.00
29.00
53.00
55.50
array:
Left X Y
* 1 0.00 45.50
2 69.50 31.00
3 121.00 55.00
4 142.50 55.00
5 156.00 61.50
* 7 0.00 43.00
8 69.50 29.00
9 121.00 53.00
RU
Phreatic
Phreatic
Right X Y
2 69.50 31.00
3 121.00 55.00
4 142.50 55.00
5 156.00 61.50
* 6 174.00 61.50
8 69.50 29.00
9 121.00 53.00
* 10 174.00 55.50
IIPhreatic surface coordinates:
No. X-coord. Y-coord.
1 0.00 32.50
I 2 69.50 29.00
3 121.00 53.00
4 174.00 55.50
"Unit weight of fluid = 0.0624
li Piezometric surface coordinates for soil A:
No. X-coord. Y-coord.
1 .00 .00
Mu
0.00
0.00
by the Tensar Corporatio
Angle
-11.78
24.99
0.00
25.71
0.00
-11.39
24.99
2.70
Soil Topline
1 Yes
1 Yes
1 Yes
1 Yes
1 Yes
2 No
2 No
2 No
"Stone columns: No
Stone column zones: (porosity = 0.000 )
Zone Col Dia in Spac g CBAR Phi Gamma Stress ratio
* 1 .0 .0 .000 .000 .000 .00
"Limits of stone columns:
* Zone X-left X-right Y-top Y-bottom
II1 .00 .00 .00 .00
Tensar geogrid placement:
is Layer Elev. X-left X-right
II 1 .00 .00 .00
Tensar geogrid strength data:
I Layer Geogrid Ult Strength Percent Design FS-Pull Percent
type Kips/ftll Ult Strength out Coverage
1 .000 .000 %o.o%o .00 .00
IGeogrid forces derated: No
* Derating constant of grid: 1.10
IIOption: Search
* Grid point X-coord Y-coord
*- 1 .00 .00
11 2 .00 .00
3 .00 .00
* 1-2 .00
11 2-3 .00
-Automatic search for critical circle:
IInitial X = 87.00 feet 44 Initial Y = 99.00 feet 44
Delta X = 1.00 feet 44 Delta Y = 1.00 feet 44
'Approximately 20 slices will be used at RMAX
Minimum tangent elevation for any failure circle is 32.00 feet 44
- Maximum tangent elevation for any failure circle is 50.00 feet 44
There are 18 increments between tangent levels
1
1
1
1
1
,
SURFICIAL SLOPE STABLILITY
SLOPE CHARACTERISTICS •
ATITTUDE OF SLOPE -A (DEGREES)=
DEPTH TO BE ANALYZED-D (FEET)=
25.71
4
PROPERTIES OF SURFICIAL SOILS
ANGLE OF INTERNAL FRICTION-PHI(DEGREES)= 13
COHESION-C(PSF)= 265
UNIT WEIGHT-G(PCF)= 120
CALCULATION -RE: STABILITY OF EARTH SLOPES, HUANG, 1983
FACTOR OF SAFETY = (C/GD)SEC(A)+.SCOS(A)TAN(PHI)
STATIC SIN(A)
FACTOR OF SAFETY = 1.7 > 1.5 Acceptable
FACTOR OF SAFETY = (C/GD)SEC(A)+[.SCOS(A)-.15SIN(A)]TAN(PHI)
SEISMIC SIN(A)+.15COS(A)
FACTOR OF SAFETY = 1.2 > 1.1 Acceptable
Western Laboratories
V V ..Geotechnrcal Enarneenna
40
y
\ .
30
-.
•• ' . Af
1
.-
•
•i ..
�`TP3
Proposed garage
LEGEND
Af Fill
Qc Colluvium
Tsh Tuffaceous sandstone and shale
y Crude strata
1"-40'
GEOLOGIC SKETCH MAP
1
•
1
1•
1
1
1
1
1
1
1
•
•
Proposed ----.._
\ ----"•• ...7---'.
\ TP2Qc
TP1
, - - - A-- - -
,
, ••
, .. ....
„ ••• ••
e --*
. ..•• • • • .*
. • • •
. •.*
. ....
, ..• ••••
, .•• ..•
,
, .•• ...•
, ..• •.
, ..
, ••••
....' ...
..-
..- strata
.•••• ....-
GEOLOGIC SECTION
•'''F•N<•?5',Tm•t•• \.
• . -
•;/•47.'". .
; . • .
•••••••,.::•,
• ..ej, • • • • .
• ••
;•-••••• .
•
•••••••irryl...• „ •
• . • . Vis•
, . •
• ...:•*;-,•:-•:•••. `s• • '.
• 4..;4e/..4-`
• "•.%44. .-::
• •
•;;;;;A:i
• ',/*
,,C): • - • • .
-,:cf • ... ,
•
Ta •
• *, ,;.. •
•'•
• .„, ......... • ,
•
/)-
• iI
-m•••• • . .‘ AZ• ......
1.>• •
../ I . ".
• .
,
AREA GEOLOGIC MAP
• . - • • . .
„•-••••••..--.e •r •
•
se
:
1 in - 2000 ft
Qal
Alluvium and artificial fill
•
I{rG.}`a��.�rt7
Stream terrace gravel
QtmQtc
Qpv
�l
Nonmarine terrace cover, Qtc
(Reddisit-brown sand. rubble:
upper Pleistocene to Recant)
Marine terrace deposits, Qtm;
those on lowest terrace consti-
tute Palos Verdes sand, Qpv
(Sand. gravel; upper Pleistocene)
UNCONFORMITV
IQtp, QI
San Pedro sand, Qsp
(Sand. silty sand, silt, crraveU
Timms Point silt, Qtp
....?1
Lomita marl, QI
(Marl, calcareous sand. trray.0
UNCONFORMI T Y
Repetto siltstone
(Glauconitie. foramini/eral siltstone)
Malaga mudstone member
(Radiolarian mudstone. diatomite)
Tv
Valmonte diatomite member
(Diatomite. diatomaceous shale,
diatomaceous mudstone)
,Tmt
X • TTot
I
Altamira shale member
(Porcelaneoue shale, cherty shale. chert,
silty shale. siltstone, phosphatic shale,
diatomite. limestone. sandstone.
conglomerate. schist -debris breccia. tuff
including Miralsste tuff bed. Trr.t, and
Portuguese tuff bed. To:: x. sons of Mai ,
concretions)
1
cc
1—
SEDIMENTARY ROCKS
UNCONFORM(T
METAMORPHIC ROCKS
Franciscan (?) schist
(Quartz-sericite schist, quarts -tale
schist. guartz•glaucophane.chill,
altered basic igneous rocks.)
IGNEOUS ROCKS
Basalt
(Intrusive and extrusive ffl )
i 0
•t_
i�
GEOMORPHIC PROVINCES
AND SOME
PRINCIPAL FAULTS
OF
CALIFORNIA
I
Generalized Geologic Units
Oumunory sodimenrory rocks
i� Ternary ledrmenrory
0u01une,7 CM Tamers soiccn.
sects of CASCADE RANGE and
M000C PLATEAU
4.
•
Crer f reeb
M .t ironblcon-Ilne..dlo
lseee
M Ic-Peleerae rnorornoroRre
and sporadic race$
ProcomDsidn re Recess sect
+ + corndlee of Ms BASIN and RANGE
Mid MOJAVE DESERT
... Goaeor►Ise Prewneo eeuroory
Gsoo .c w.l t»undesT
— Foufl
(F«+ + ♦ \
+ + 4 + + + ♦ + } \\.
++M•p«++' ♦.P .`�
4 + + + + + + ♦ + + .G'- +
• • + + + + +• •jr + + + + • qt.+ +
4 r. + + ♦ + + •.4 + + • + : + +\
T + + + + } + + + + + + + •1
+++•+++o.+ ♦+ ••t.,
• • + + + + + +
TRAN:ntir.:r }= : , ; `d"`r' ;; 'Al`jGES' ♦' ♦' + tt 4 + * ' } i?
• ♦ ♦ „1 + }i
• ♦ • +l
.
• + +
• ♦ •
L ♦ ♦
SITE
CDMG
REGIONAL GEOLOGIC MAP 1 in -100 mi
1
0
0 .14
1923
1992
1906
1989
O Magnitude 6.0 to 6.9
OMagnitude 7 and
greater
1868
0
�838
1927 SO
1812
19150
1954
0 0�a 1954
N. 0 1932
\ 0
0 •\
1872\•\
1857 0 N.
CO \
1952 0 \
1812
1992
SITE 0 i
e
_....0-•,o
CDMG
EPICENTER MAP 1 in- 150 mi
,,,
$$ • rim,' srmis
916
857
30 .
...._.......!.. 6-1..
, 11193\._
- -......;
ENTURA ‘
****"...;::-=`•--rfc. /.0. 43 1971
,e...igj. t.
.—,IZ
--;'4 —.4rEPkaA.loo ..3.10... ITS
kti.c.. ---...44o•.•
,/.-.....!
11355 ,76.1:„..mywco, i -144--.--,•T ...00F.'"C.:,.'" .:„..c
"(MT 00)40 Ns" L
.... ..„
14T1JRA
1.465
1. ANGE ES
$M ruspo.Noo nuu
**--..:301439 k).% LOS 1920
trio •••••••
44: SANTA
1.6116
• ORANG
• cttr- "."
•
14./2%. 1933
COMM.*
IsAftwe
4550MM* OF ENGINEERING GEOLOGisT3
1973
I699
RIVERSIDE
1923
146.3
1910
.*:Ze...•
•
.p..,.si. Pr.row .
'... • .„/
CAOr o aut.l.
• \ • • S A.›. c..Pi
'‘... N A.. 8 E
R
1 s•\,. % -.5.\,..4. \\ 0 .15Gaff t...1.4
\ ‘'.
4'°0 C:14* S *) \\ .
. SA IP • ...
\ " 4.
C., : ,:.• :•.\• • \
•!0.
N..z..V% is • •
it • I... 11 •:
• :•.\,‘
1907 „„..limi% T.
e.,3!-Ve
SAN
OiEGO
4
INC40
•
—_194—
samits.;
1918 • ug.
146A
Pau%
SPNINGs
1899
1.17+
1937
ra60
<)". t••••••...1t
•
le9S4 A N_ Alum
--- G
1856
lin - 30mi
MAJOR EARTHQUAKES AND RECENTLY ACTIVE FAULTS
IN THE SOUTHERN CALIFORNIA REGION
EXPLANATION'
ACTIVE FAULTS
FAULT MAP
1889
14 7*
1952
3177
EARTHQUAKE LOCATIONS
Approximate epicentral orea of earthquakes